Work Summary:
Construction has been progressing nicely this last month with multiple areas near completion. All classrooms have now received paint, casework, finish flooring and new ceilings. The 1st floor corridor is ready for finish floor installation while the 2nd floor is receiving the new ceiling system. The dust collector has been set for the wood shop. The fire barrier near the HS gym is ongoing. The demo for the new bathrooms located near the HS gym has begun.
The following areas are substantially complete and are now being utilized by the district:
➢ New Main Office and Entryway (Old Library, Computer Lab and Distance Learning)
➢ All Bathrooms are now completed and available to the District
➢ New Art Room (Old Health 1A and Lab 1B)
➢ Renovated Classrooms102, 103, 104, 105,106, 112, 116(Choir)and 206
➢ Basement Corridor (Faculty Room, FACS, Publications and Bathrooms)
➢ HS Cafeteria and Senior Lounge
➢ New Media Center(Minus Quiet Study)
➢ New Band Area and Associated Rooms/Offices
➢ Majority of all the Classrooms throughout the Building
Progress details:
HS Cafeteria& Senior Lounge
➢ The built–in folding tables have been installed
➢ Only Punchlist items remain
New Media Center (Old Main Office and Entry Way)
➢ Final paint needed
➢ Floor Finishes to be installed in early August
➢ Ceiling has been installed
2nd Courtyard Infill and Associated Rooms
➢ Casework has been installed
➢ District to place furniture
➢ Gross Electric needs to move one (1) outlet for Distance Learning per BOCES
➢ Projector screen and smart boards need to beplaced
New Band Area (Old Temp Cafeteria)
➢ Rubber wall base hasbeen installed
➢ Bast to provide single cabinet, sink installation will follow2ndFloor Classrooms
➢ New Ceiling Systems are installed
➢ Final paint is complete
➢ District has begun to set–up for teachers
1st and 2nd Floor Corridors
➢ Fire Alarm Devices are substantiallyin place
➢ New Ceiling Systems should be in place by the end of the month(both floors)
➢ Stairwelltreads havebeen replaced and now receiving the new rubber treads
➢ Self–Leveleris to be placed in the corridors on both floors August 6thand 7th
➢ Final floor finishinstallation to follow
➢ Final light installation on the 2ndfloor ongoing
New Fire Wall near HS Gymnasium
➢ New slab has been poured
➢ Door frames are placed
➢ Walls have been constructed
➢ Final paint to occur in early August
➢ Final floor finishes to occurat the end of August
Wood and Metal Shop
➢ New Dust Collector has beenset –duct work to follow
➢ RTU duct works has been installed
➢ Waiting on Steel for RTU’s 9 & 10
Additional Project Updates
➢ Demo for the new bathrooms near the HS Gym has started
➢ Remaining Doors/Hardware have arrived on site–installation on going
➢ Glass installation to continue in early August
➢ Kitchen wall work to being in early August with gross electric performing demo