January Capital Project Update

WORK ACTIVITY DURING REPORTING PERIOD: Phase II – B is progressing nicely with a few schedule changes.  Rough-in from all trades in the basement corridor is substantially complete and installation of finishes has started. Work in the HS Cafeteria remains on-going.  Demo in the Courtyard Infill on both levels is substantially complete and rough-in of mechanicals has started.  Installation of a new sidewalk in the front (street view) of the building is now complete. 

Capital Construction Project:

The following areas are substantially complete and are now being utilized by the District:

  • New Main Office and Entryway (Old Library, Computer Lab and Distance Learning)
  • First and Second Floor Bathrooms (Front of the Building)
  • New Art Room (Old Health 1A and Lab 1B)
  • Renovated Classrooms 105, 106 and 206

 

Phase B Construction:

Basement Corridor (Bathrooms, New FACS 12, Publications)

  • Demo from all trades is substantially complete
  • Rough-In from all trades is substantially complete
  • New FACS and Faculty Room have been painted, ceilings installed, and electrical devices installed
  • Casework is complete

Basement Corridor (Bathrooms, New FACS 12, Publications) – Continued 

  • Ductwork installation throughout the space is substantially complete
  • Ceilings in the corridor installed
  • Flooring installed

 

Exterior Window Wells (Facing Main Street)

  • Concrete work is substantially complete
  • Windows are installed

 

HS Cafeteria 

  • Demo is complete
  • Skylights have been installed
  • Framing and drywall is substantially complete
  • Electrical rough-in is also substantially complete
  • New wall opening to Senior Lounge to be cut-in the week of 11/25

 

New Media Center (Old Main Office and Entry Way)

  • Demo is on-going in this area
  • Electrical demo is on-going with fire alarm rough-in
  • Structural lintels have been placed
  • New openings have been placed

 

Courtyard Infill and Associated Rooms

  • All trades demo is substantially complete
  • Fire proofing is complete
  • Sheetrock installation is on-going
  • Multiple electrical panels have been relocated
  • Ductwork installation has commenced

 

Bathrooms 108 and 208A/B

  • Tile installation in Bathroom 108 completed
  • Bathroom fixtures installed
  • Faculty bathrooms 208A and B have been framed

Additional Project Updates:

  • The sidewalk in front of the building (street view) is now complete and has since been turned over to the District.
  • New roof caps installed. The new windowsills are now complete.
  • The basement corridor rooms turned over during the beginning part of December.