WORK ACTIVITY DURING REPORTING PERIOD: Phase II – B is progressing nicely with a few schedule changes. Rough-in from all trades in the basement corridor is substantially complete and installation of finishes has started. Work in the HS Cafeteria remains on-going. Demo in the Courtyard Infill on both levels is substantially complete and rough-in of mechanicals has started. Installation of a new sidewalk in the front (street view) of the building is now complete.
Capital Construction Project:
The following areas are substantially complete and are now being utilized by the District:
- New Main Office and Entryway (Old Library, Computer Lab and Distance Learning)
- First and Second Floor Bathrooms (Front of the Building)
- New Art Room (Old Health 1A and Lab 1B)
- Renovated Classrooms 105, 106 and 206
Phase B Construction:
Basement Corridor (Bathrooms, New FACS 12, Publications)
- Demo from all trades is substantially complete
- Rough-In from all trades is substantially complete
- New FACS and Faculty Room have been painted, ceilings installed, and electrical devices installed
- Casework is complete
Basement Corridor (Bathrooms, New FACS 12, Publications) – Continued
- Ductwork installation throughout the space is substantially complete
- Ceilings in the corridor installed
- Flooring installed
Exterior Window Wells (Facing Main Street)
- Concrete work is substantially complete
- Windows are installed
HS Cafeteria
- Demo is complete
- Skylights have been installed
- Framing and drywall is substantially complete
- Electrical rough-in is also substantially complete
- New wall opening to Senior Lounge to be cut-in the week of 11/25
New Media Center (Old Main Office and Entry Way)
- Demo is on-going in this area
- Electrical demo is on-going with fire alarm rough-in
- Structural lintels have been placed
- New openings have been placed
Courtyard Infill and Associated Rooms
- All trades demo is substantially complete
- Fire proofing is complete
- Sheetrock installation is on-going
- Multiple electrical panels have been relocated
- Ductwork installation has commenced
Bathrooms 108 and 208A/B
- Tile installation in Bathroom 108 completed
- Bathroom fixtures installed
- Faculty bathrooms 208A and B have been framed
Additional Project Updates:
- The sidewalk in front of the building (street view) is now complete and has since been turned over to the District.
- New roof caps installed. The new windowsills are now complete.
- The basement corridor rooms turned over during the beginning part of December.